The fastest way to slow down a VPX system integration project is to rush it. Once a chassis arrives, the instinct is to plug in every board, apply power, and see what happens. That rarely goes well. A slower, more methodical approach consistently yields better results in less time, because it isolates problems instead of stacking them on top of each other.
In this TIP, we examine how to mitigate integration challenges by separating two specific areas of bring-up, which is the process of powering on and verifying a newly designed hardware system or board for the first time. Addressing the development system on the bench is the first step, while the second focuses on booting a rugged set of the same board models in the deployment chassis.
Configuration, bring-up, and debug are usually easier in a lab tabletop development chassis, where there are fewer variables to manage. Rear transition modules can often be used to reach board I/O, such as on single board computers and Ethernet switches, and boards in their air-cooled configuration sometimes offer front I/O with commercial connectors, simplifying initial bring-up further. Starting directly with the rugged chassis and rugged boards adds the complexity of unfamiliar I/O connectivity, both inside and outside the chassis, on top of everything else being tested for the first time.
Once you have the reference set of boards established in the development system, bring up the rugged set of the same board models in a rugged deployment chassis. Another advantage to using the 2-step approach is you can use the development chassis as a reference for comparison when bringing up and debugging the rugged chassis.

An integration plan does not need to be overly complicated to be useful. Even an informal checklist keeps the process moving through one variable at a time, so problems are easy to trace and easy to reverse. A starting outline typically looks something like this:
This outline can serve as a basis for testing most boards within a system. Use it as a guideline to map out the strategy you need for your own implementation.
Make sure you apply this process across your entire system, adding each remaining board in the same way: install it, verify its interfaces, confirm communication with the boards already in the system, and test its I/O before moving to the next one.
Working through a plan like this introduces a few variables at a time, so if something does not come up cleanly, it’s a straightforward process to trace things back and revert. If you skip the sequence and power everything up at once, each of those variables are now in play simultaneously, which makes root-causing an integration issue far harder than it needs to be.
For nearly 40 years, Elma Electronic has supplied the embedded computing industry with rugged, high-quality products spanning backplanes, chassis, boards, and fully integrated subsystems. Our engineering teams work directly with customers across the full integration lifecycle, not just at point of sale.
Elma TIPs are a direct product of that ongoing collaboration. We field pre-sales questions as customers work through requirements, technical questions during preliminary and critical design reviews, and post-sales questions on both standard and custom products. When the same question surfaces more than once, it is usually worth documenting and sharing. That is what this series is for.
Have an integration question specific to your program? Reach out via our Contact Us form and we will connect you with the right resource.

用于要求苛刻的应用的坚固平台历来受到高性能处理器和其他关键系统组件有限的工作温度范围的限制。这些应用通常在极具挑战性的温度下运行,而高性能处理器通常不具备这些工作温度范围。到目前为止。

在过去的几年中,系统集成挑战发生了变化,制造商在集成、故障排除和系统升级方面提出了新的要求。本博客探讨了Elma及其合作伙伴接口概念、并行技术和EIZO Rugged Solutions如何定义合作时在我们的生态系统中合作的意义。